Progress for 08/09/2021

Bar top is being installed. Chairs and table tops are in. Kitchen is really taking shape. Behind the glass partition there will be 3 vertical pods from downstairs.

Progress for 08/01/2021

Things are happening so fast now, we can’t keep up posts on our blog. Flooring is in. Don’t mind the brown paper covering the floor, it’s for protection during the build-out. Tile work is done on the bar and kitchen walls.

Oh my, fresh greens from Old Market Greens downstairs make all the difference! We’ve built an elevator just to bring the pods up from downstairs into the kitchen. Fresh is an understatement for these greens.

Progress for 07/20/2021

The front outdoor sign is done! Thanks to American Lift & Sign Company for the build. Install should be Thursday. The growing towers for The Vertical Farm located in the basement of Gather-Omaha are built. We have some finishing up details, but planting will happen soon. The Vertical Farm will have a view room. You will be able to gather with friends, see and taste the latest harvest and buy some greens to go. Booths arrived for the back room. They are in our signature olive green, same color as our booths at Gather-Jackson Hole.

Progress for 07/18/2021

We’re getting so, very close. Getting to all the details. Front room is drywalled and painted. The front room will have a wonderful view of outside activities on Howard Street with large picture windows. Kitchen appliances have started to arrive. The kitchen will be fully visible from the front room. Bar has been tiled and coolers installed. Next the bar tops.

Progress for 07/01/2021

Happy July all! Progress is really happening fast at Gather In Omaha. Ceiling is painted, lighting is being installed. Drywall is done and painting has started. Front patio area is all cleared out. Next tweek he concrete will be poured. It’s starting to look like a restaurant!